Buildings:


Facilities Master Plan

Possible Clinton Climate Initiative (CCI) Projects

Building Priority Brief Description Estimated Cost
South Central Plant 1 Replace a cooling tower $200,000
Various 3 Active Solar Panels $0
Various 4 Window Tinting $0
TV2, TV3, TV4 5 Fan Coil Units $235,000
South Central Plant 6 Convert Metasys Data Collection to UES Control System $150,000
South Central Plant 7 Remove ACM - Install Closed Insulation $155,000
Moler Hall 8 Numerous Upgrades, including UES DDC $350,000
Science 9 Convert to UES $60,000
Pipe Rack 10 Replace valves and insulation $600,000
TV 2 11 Air Handling Unit Repairs $20,000
Bonner Hall 12 Convert to UES $65,000
Student Center 13 Convert to UES $50,000
TV 1 14 Replace Main Air Handling Units $165,000
Natatorium Mech Room 15 Replace the pool water heater with Solar Heating $45,000
Natatorium Mech Room 16 Replace the filter $30,000
Tucker Hall 17 HVAC Replacement - Convert to Central Plant & EUS $200,000
TV 6 18 Replace condenser $10,000
TV 5 19 Replace 2 condensers $15,000
TV 9 20 Replace package system $20,000
ALC 21 Replace a condenser $7,500
Day Care Center 22 Replace condensing equipment and insulate piping $15,000
Science 23 Rework Insulation on AHU and Pipes $55,000
TV 2 24 Air Compressor for A/C $10,000